The purpose of the security of payment legislation is to promote cashflow down the contracting chain. It does this in two ways. First, it contains a number of general protections for contractors. Second, it contains a mechanism for the (relatively) speedy recovery of progress payments.
The legislation applies to building work carried out in NSW. Certain types of contract are excluded, the most notable being a construction contract for carrying out residential building work, as defined in the Home Building Act 1989 (NSW).
The comments below only apply to construction contracts covered by the Act.
Some of the general protections for contractors under the legislation are as follows:
The Act gives contractors a statutory right to receive progress payments. This right operates in addition, and parallel, to any right you might have to receive progress payments under your contract.
The process for recovering progress payments is the better-known part of the Act, and where the legislation derives its name from.
In short:
Adjudication under the security of payment legislation involves the determination of dispute over a progress claim by an independent adjudicator.
The adjudicator is not a judge (and is often not a lawyer), and is appointed by an independent ‘nominating authority’. You can find a list of nominating authorities here. If you apply for adjudication, you make your application to one of those authorities, who then appoints the adjudicator for you.
Your adjudication application is a written document that must be sent to the nominating authority within a fixed period – usually 10 business days from the date you receive the payment schedule. You must also serve a copy of your application on the client. Most nominating authorities have their own application form.
By making an application, you will assume responsibility for paying the adjudicator's fee. If your application is successful, you would normally be able to recover this cost (or most of it) from your client.
Your client will only have a short time to respond to your application – either 5 business days from receiving the application, or 2 business days after the nominating authority has appointed an adjudicator and accepted their application, whichever is longer.
Importantly, your client can only include reasons for withholding payment in its adjudication response if those reasons were included in its payment schedule.
A claimant has an express right to withdraw an adjudication application at any time before a determination has been made. The respondent may object to a withdrawal if an adjudicator has been appointed.
Once the time for your client to provide a response has lapsed, the adjudicator is required to determine the application. Unless the parties agree to extend the timeframe, the adjudicator’s decision is required to be issued within 10 business days after the date on which the adjudicator notified the claimant and the respondent of their acceptance of the application.
Once an adjudication determination has been issued, the respondent (your client) must pay the ‘adjudicated amount'.
If your client does not pay, you will have a right to suspend work (subject to giving the required notice) and you will also have the right to obtain an ‘adjudication certificate’ and proceed to file that in court to obtain judgment.
There are very few situations where an adjudication determination can be set aside. In most cases, the adjudicated amount must be paid. However, where the adjudication determination is affected by jurisdictional error, the Act give the court an express right to set aside that adjudication determination. If only part of a determination is affected by jurisdictional error, the court may set aside that part only, while confirming the balance of the determination.
Finally, it is important to recognise that a payment under the Act is an interim payment only, effectively a payment on account. If you receive an amount under the Act to which you are not contractually entitled, your client will have the right to recover the difference from you. This is where the legislation gets its name from – any payment you recover under this statutory payment is effectively ‘security’ pending the determination of the final position under the contract.