Assuming your dispute has just arisen, you have five basic options:
1. Informal dispute resolution
2. Security of payment
3. The contractual process
4. Alternative dispute resolution
5. Urgent court application
These processes are not mutually exclusive. That is, you may be able to run multiple processes at the same time.
There is nothing to prevent you from contacting the other party to discuss the dispute. You can make a settlement offer at any time, and you can also make suggestions about different ways the dispute can be resolved.
Most disputes, at least small ones, are resolved through negotiation and without the need for any formal process. The greatest benefit of an informal process (like an unsolicited settlement offer) is that it is quick and cheap in comparison with the alternatives. The greatest disadvantage is that it is not guaranteed to produce a result.
The security of payment legislation gives contractors a statutory right to receive progress payments for the performance of construction work or the supply of related goods or services.
In some states:
Payments made under the security of payment legislation are interim only. If the legislation results in a contractor receiving more than they would be entitled under the contract, the principal can make a claim against the contractor to ‘claw back’ the difference.
However, even though a contractor’s entitlements under the security of payment legislation are interim only, it is not uncommon for applications under the security of payment legislation to result in a final resolution of the claim. This is because either:
The second scenario above is a classic illustration of two dispute resolution processes (security of payment legislation and an informal process) being run concurrently to result in a final resolution of a claim.
Keep in mind that a security of payment remedy may not be available in all instances. This will depend on a number of factors, including the location of the project (as the law differs between States), the nature of the project (not all project are covered), the nature of the claim (not all claims can be pursued) and the availability of a ‘reference date’. You can read more about security of payment here.
AS 4000 prescribes a 3 step process for resolving a dispute:
Clause 42.1 sets out the requirements for a notice of dispute. The notice is important because it sets out the parameters of the dispute that may ultimately be referred to arbitration.
Within 14 days of receiving a notice of dispute, the parties are required (by clause 42.1) to confer at least once in an effort to resolve the dispute or agree on a method for doing so. The parties are required to meet in good faith, with each of them being represented by a person authorised to resolve the dispute on their behalf.
If the parties are unable to resolve the dispute or agree on an alternative process within 28 days of the notice of dispute being served, either party may refer the dispute to arbitration. Arbitration is very similar to a court process, except that the adjudicator is privately appointed (and not a judge). You can read more about arbitration here.
This process is designed to ensure that, if the parties are unable to resolve a dispute through discussion and negotiation, there is a process (arbitration) that will ultimately produce a binding outcome.
The problem with traditional dispute resolution processes, and particularly arbitration and litigation, is that they are incredibly time-consuming and expensive. As a result, parties often look for alternative ways for their disputes to be determined.
Common alternatives are:
Sometimes, urgent court intervention is required (such as an injunction). Where this is the case, the procedure in AS 4000 does not prevent a party from approaching the court – and the court may be the only avenue for a party to obtain relief.
Which approach is best?
As you may have gathered from the above, there is no ‘one-size-fits-all’ approach. Regardless of the nature of your dispute, it is important to keep in mind that dispute resolution is a process. Choosing the right process (or the right combination of processes) is absolutely critical to ensuring the best possible result.