This page explains how to respond to an adjudication application under the Building and Construction Industry Security of Payment Act (NSW).
If you aren't sure how to respond to an adjudication application under the NSW security of payment legislation, we suggest the following approach:
Each of these steps is explained in more detail below.
You can read more about the NSW security of payment legislation here. If you're facing a payment issue with a contractor or supplier, one of our workshops may be of interest. Read more here.
Two things will determine this:
You may only have 5 business days after receiving the application.
The time for serving your adjudication response is strict and cannot be extended, regardless of the value of the claim or the volume of material prepared by the claimant.
Once you have determined when your response is due, you should think about how you plan to serve it.
Most nominating authorities will accept service electronically (ie by email or document upload), and you can contact them to find out. Sometimes (but not always) the nominating authority will send you a note explaining how you can respond.
If you will be serving a large volume of material, you should ensure that you allow plenty of time to make sure it can be safely delivered before the deadline.
If you think you might need assistance preparing your adjudication response, it’s critical that you seek that help as early as you can. Some parts of the Act are highly technical, and an experienced construction lawyer will be able to help you work through the issues. (You can contact us here.)
No matter how good they are, a lawyer will not be able to achieve much if they only receive instructions a short time before your response is due.
3. Consider whether there are any jurisdictional issues.
Just because you have received a document that purports to be an adjudication application, this does not necessarily mean that it is a valid application under the Act.
This is an area where a specialist construction lawyer can help.
For an adjudication application to be valid, there must be (among other things):
In relation to the third point, there needs to have been a date on (or from) which the contractor is entitled to make a claim for payment. (See section 13, here.) If the contract does not prescribe a date, the default position under the Act will apply (and you can find the details here). Importantly, only one payment claim can be made in any particular named month. (See section 13(5), here.)
Unless all of the relevant conditions are satisfied, an adjudication application will not be valid. If the application is invalid because of a jurisdictional reason, the adjudicator may not be authorised to issue a determination, regardless of the merits of the underlying claim.
Where an adjudicator determines a claim that is affected by jurisdictional error, the Act gives the court an express right to set aside that decision. If only part of a determination is affected by jurisdictional error, the court may set aside that part only, while confirming the balance of the determination.
The Act gives a statutory right to eligible persons to recover progress payments for construction work and/or related goods and services.
Section 9 (here) explains how these progress payments are to be calculated. Relevantly, the value of the payment will be:
Anything that falls outside of this cannot be claimed.
For example, claims for general damages will not normally be allowed under the Act. This is because most construction contracts do not contemplate general damages being taken into account in assessing the value of a progress payment, and general damages are unrelated to the value of construction work and related goods and services.
If there are amounts included in the claim that cannot be claimed under the Act, these should be identified in your adjudication response and brought to the adjudicator’s attention.
Section 20 (here) sets out the requirements for adjudication responses.
Relevantly, an adjudication response:
The last point above does not prevent you from addressing jurisdictional issues in your response. However it does mean that you cannot introduce any new, non-jurisdictional reasons for withholding payment that were not included in your payment schedule. (You can read more about payment schedules here.)
Once you understand what can be included in your adjudication response, it is time to start putting the response together, including the supporting documentation.
Adjudication responses can sometimes be lengthy documents. Usually an adjudication response would include:
Once your response is finalised, make sure you serve it on the adjudicator before the deadline. Late responses cannot be considered.
Also note that, pursuant to section 20(3) of the Act (here), a copy of the response must be served on the claimant.